On site now

3 jobs running, and the programme for each one.

Every contract we sign carries a programme: eight stages, each with a number of weeks and a payment percentage, agreed before anybody breaks ground. These are those programmes, walked forward to today: the bars are the stages, the stage marked on now is where the job has got to this week, and the schedule under each board shows which payments have been released and which one is next.

Beechwood Avenue, Kingston 8

Two-storey block house · 232 m²
Contract JMD 41,760,000 · 30 week programme
Started 02 Jul 2026, Nine on site, two subcontract gangs

30 weeks Programme signed at contract
Handover is week 30
  1. 01 / 8 Set out, footings and foundation 3 weeks · 10% of the contract week 1 to 3
  2. 02 / 8 Blockwork to ring beam 5 weeks · 15% of the contract week 4 to 8
  3. 03 / 8 Roof or suspended slab 4 weeks · 15% of the contract week 9 to 12
  4. 04 / 8 Windows, doors and external render 4 weeks · 12% of the contract week 13 to 16
  5. 05 / 8 Plumbing and electrical rough-in 3 weeks · 12% of the contract week 17 to 19
  6. 06 / 8 Plaster, screed and tiling 4 weeks · 14% of the contract week 20 to 23
  7. 07 / 8 Joinery, fittings and paint 4 weeks · 12% of the contract week 24 to 27
  8. 08 / 8 Snag list and handover 3 weeks · 10% of the contract week 28 to 30

Stage payments on this job

StageSharePayment, JMDStatus
Set out, footings and foundationSigned off: Engineer, steel before the pour 10% 4,176,000 After week 3 sign-off
Blockwork to ring beamSigned off: Client walks the openings 15% 6,264,000 After week 8 sign-off
Roof or suspended slabSigned off: Watertight after rain 15% 6,264,000 After week 12 sign-off
Windows, doors and external renderSigned off: Openings sealed, render cured 12% 5,011,200 After week 16 sign-off
Plumbing and electrical rough-inSigned off: Pressure test, wall photographs 12% 5,011,200 After week 19 sign-off
Plaster, screed and tilingSigned off: Shower flood test, tile set-out 14% 5,846,400 After week 23 sign-off
Joinery, fittings and paintSigned off: Electrical certificate 12% 5,011,200 After week 27 sign-off
Snag list and handoverSigned off: Client snag list cleared 10% 4,176,000 After week 30 sign-off
Contract sum, fixed at signing 100% 41,760,000 Invoiced stage by stage

5% is held back from every stage payment as retention and released 90 days after handover. 2 variations signed on this job so far, worth JMD 386,000, added to the contract sum above. Weather days used: 2 of 5.

About this job

A family house on a tight corner plot: two floors, four bedrooms, a poured stair and a carport. The steel came in one order at the start of the job, which is why the price held when the price of steel moved in August.The crane hire is shared with a job two streets over, and that saving is in the price rather than in our pocket.

Private client, house for their own use · Nine on site, two subcontract gangs · This job on its own page

Shortwood Road shop fit-out

Shop or office fit-out · 96 m²
Contract JMD 14,880,000 · 18 week programme
Started 20 Aug 2026, Five on site

18 weeks Programme signed at contract
Handover is week 18
  1. 01 / 8 Set out, footings and foundation 2 weeks · 10% of the contract week 1 to 2
  2. 02 / 8 Blockwork to ring beam 3 weeks · 15% of the contract week 3 to 5
  3. 03 / 8 Roof or suspended slab 2 weeks · 15% of the contract week 6 to 7
  4. 04 / 8 Windows, doors and external render 2 weeks · 12% of the contract week 8 to 9
  5. 05 / 8 Plumbing and electrical rough-in 2 weeks · 12% of the contract week 10 to 11
  6. 06 / 8 Plaster, screed and tiling 3 weeks · 14% of the contract week 12 to 14
  7. 07 / 8 Joinery, fittings and paint 2 weeks · 12% of the contract week 15 to 16
  8. 08 / 8 Snag list and handover 2 weeks · 10% of the contract week 17 to 18

Stage payments on this job

StageSharePayment, JMDStatus
Set out, footings and foundationSigned off: Engineer, steel before the pour 10% 1,488,000 After week 2 sign-off
Blockwork to ring beamSigned off: Client walks the openings 15% 2,232,000 After week 5 sign-off
Roof or suspended slabSigned off: Watertight after rain 15% 2,232,000 After week 7 sign-off
Windows, doors and external renderSigned off: Openings sealed, render cured 12% 1,785,600 After week 9 sign-off
Plumbing and electrical rough-inSigned off: Pressure test, wall photographs 12% 1,785,600 After week 11 sign-off
Plaster, screed and tilingSigned off: Shower flood test, tile set-out 14% 2,083,200 After week 14 sign-off
Joinery, fittings and paintSigned off: Electrical certificate 12% 1,785,600 After week 16 sign-off
Snag list and handoverSigned off: Client snag list cleared 10% 1,488,000 After week 18 sign-off
Contract sum, fixed at signing 100% 14,880,000 Invoiced stage by stage

5% is held back from every stage payment as retention and released 90 days after handover. 1 variation signed on this job so far, worth JMD 92,500, added to the contract sum above. Weather days used: 0 of 5.

About this job

A pharmacy going into a shell unit. The landlord allows work from seven to five on weekdays only, so the programme is built on weekday hours and nothing is promised for a Saturday.The shopfront glass is a twelve week lead item and was ordered in week one, before we broke a single wall.

Pharmacy, first branch · Five on site · This job on its own page

Jacks Hill one-storey house

One-storey block house · 148 m²
Contract JMD 22,940,000 · 26 week programme
Started 02 Apr 2026, Six on site, painters finishing

26 weeks Programme signed at contract
Handover is week 26
  1. 01 / 8 Set out, footings and foundation 3 weeks · 10% of the contract week 1 to 3
  2. 02 / 8 Blockwork to ring beam 4 weeks · 15% of the contract week 4 to 7
  3. 03 / 8 Roof or suspended slab 3 weeks · 15% of the contract week 8 to 10
  4. 04 / 8 Windows, doors and external render 3 weeks · 12% of the contract week 11 to 13
  5. 05 / 8 Plumbing and electrical rough-in 3 weeks · 12% of the contract week 14 to 16
  6. 06 / 8 Plaster, screed and tiling 4 weeks · 14% of the contract week 17 to 20
  7. 07 / 8 Joinery, fittings and paint 3 weeks · 12% of the contract week 21 to 23
  8. 08 / 8 Snag list and handover 3 weeks · 10% of the contract week 24 to 26

Stage payments on this job

StageSharePayment, JMDStatus
Set out, footings and foundationSigned off: Engineer, steel before the pour 10% 2,294,000 After week 3 sign-off
Blockwork to ring beamSigned off: Client walks the openings 15% 3,441,000 After week 7 sign-off
Roof or suspended slabSigned off: Watertight after rain 15% 3,441,000 After week 10 sign-off
Windows, doors and external renderSigned off: Openings sealed, render cured 12% 2,752,800 After week 13 sign-off
Plumbing and electrical rough-inSigned off: Pressure test, wall photographs 12% 2,752,800 After week 16 sign-off
Plaster, screed and tilingSigned off: Shower flood test, tile set-out 14% 3,211,600 After week 20 sign-off
Joinery, fittings and paintSigned off: Electrical certificate 12% 2,752,800 After week 23 sign-off
Snag list and handoverSigned off: Client snag list cleared 10% 2,294,000 After week 26 sign-off
Contract sum, fixed at signing 100% 22,940,000 Invoiced stage by stage

5% is held back from every stage payment as retention and released 90 days after handover. 3 variations signed on this job so far, worth JMD 615,000, added to the contract sum above. Weather days used: 4 of 5.

About this job

A house on a slope, which meant a retaining wall to the rear before anything else could start. That wall was priced as its own line and signed before we broke ground.Four weather days went on the roof in June. The programme absorbed them, so the handover date has not moved.

Returning client, second house · Six on site, painters finishing · This job on its own page

How the programme is written

Why a date on this page can be trusted, and when it moves.

What fixes a date

  • The stage weeks come from the contract, signed by both of us before the first pour.
  • Long-lead items are ordered in week one. Shopfront glass, windows and joinery are the three that sink programmes here.
  • Each stage is signed off by somebody: the engineer, the electrician, or you.
  • The next stage does not start until the one before it is signed, which is why the bars do not overlap.

What moves a date

  • Rain beyond the 5 weather days in the contract. Days are logged as they happen, in the report.
  • A variation you sign, which states on its face how many days it adds.
  • Something hidden that the drawings could not show: termite damage, a slab 40 mm out of level, a water main where the footing goes.
  • An item you chose to supply yourself arriving late. That date is on the programme too.

Nothing else moves a date. Not another client's job, not a truck, not a public holiday: those are our problem and they are already in the weeks you see.

What is in a Friday report

Five things, every week, whether or not the week went well.

  1. Done this week. What was actually completed, not what was worked on.
  2. Next week. What starts, and anything we need from you before Monday.
  3. Materials and lead items. What is on site and what is still on order with a date.
  4. Weather. Hours or days lost, and how many of the 5 weather days are left.
  5. Money. Whether a stage completed, what is invoiced, and any variation waiting for your signature.