Two-storey block house · 232 m²
Contract JMD 41,760,000 · 30 week programme
Started 02 Jul 2026, Nine on site, two subcontract gangs
30 weeks
Programme signed at contract
Handover is week 30
Stage
week 1week 15week 30
-
01 / 8
Set out, footings and foundation
3 weeks · 10% of the contract
week 1 to 3
-
02 / 8
Blockwork to ring beam
5 weeks · 15% of the contract
week 4 to 8
-
03 / 8
Roof or suspended slab
4 weeks · 15% of the contract
week 9 to 12
-
04 / 8
Windows, doors and external render
4 weeks · 12% of the contract
week 13 to 16
-
05 / 8
Plumbing and electrical rough-in
3 weeks · 12% of the contract
week 17 to 19
-
06 / 8
Plaster, screed and tiling
4 weeks · 14% of the contract
week 20 to 23
-
07 / 8
Joinery, fittings and paint
4 weeks · 12% of the contract
week 24 to 27
-
08 / 8
Snag list and handover
3 weeks · 10% of the contract
week 28 to 30
- Today
Stage payments on this job
5% is held back from every stage payment as retention and released
90 days after handover.
2 variations signed on this job so far, worth
JMD 386,000, added to the contract sum above.
Weather days used: 2 of 5.
About this job
A family house on a tight corner plot: two floors, four bedrooms, a poured stair and a carport. The steel came in one order at the start of the job, which is why the price held when the price of steel moved in August.The crane hire is shared with a job two streets over, and that saving is in the price rather than in our pocket.
Private client, house for their own use · Nine on site, two subcontract gangs · This job on its own page
Shop or office fit-out · 96 m²
Contract JMD 14,880,000 · 18 week programme
Started 20 Aug 2026, Five on site
18 weeks
Programme signed at contract
Handover is week 18
Stage
week 1week 9week 18
-
01 / 8
Set out, footings and foundation
2 weeks · 10% of the contract
week 1 to 2
-
02 / 8
Blockwork to ring beam
3 weeks · 15% of the contract
week 3 to 5
-
03 / 8
Roof or suspended slab
2 weeks · 15% of the contract
week 6 to 7
-
04 / 8
Windows, doors and external render
2 weeks · 12% of the contract
week 8 to 9
-
05 / 8
Plumbing and electrical rough-in
2 weeks · 12% of the contract
week 10 to 11
-
06 / 8
Plaster, screed and tiling
3 weeks · 14% of the contract
week 12 to 14
-
07 / 8
Joinery, fittings and paint
2 weeks · 12% of the contract
week 15 to 16
-
08 / 8
Snag list and handover
2 weeks · 10% of the contract
week 17 to 18
- Today
Stage payments on this job
5% is held back from every stage payment as retention and released
90 days after handover.
1 variation signed on this job so far, worth
JMD 92,500, added to the contract sum above.
Weather days used: 0 of 5.
About this job
A pharmacy going into a shell unit. The landlord allows work from seven to five on weekdays only, so the programme is built on weekday hours and nothing is promised for a Saturday.The shopfront glass is a twelve week lead item and was ordered in week one, before we broke a single wall.
Pharmacy, first branch · Five on site · This job on its own page
One-storey block house · 148 m²
Contract JMD 22,940,000 · 26 week programme
Started 02 Apr 2026, Six on site, painters finishing
26 weeks
Programme signed at contract
Handover is week 26
Stage
week 1week 13week 26
-
01 / 8
Set out, footings and foundation
3 weeks · 10% of the contract
week 1 to 3
-
02 / 8
Blockwork to ring beam
4 weeks · 15% of the contract
week 4 to 7
-
03 / 8
Roof or suspended slab
3 weeks · 15% of the contract
week 8 to 10
-
04 / 8
Windows, doors and external render
3 weeks · 12% of the contract
week 11 to 13
-
05 / 8
Plumbing and electrical rough-in
3 weeks · 12% of the contract
week 14 to 16
-
06 / 8
Plaster, screed and tiling
4 weeks · 14% of the contract
week 17 to 20
-
07 / 8
Joinery, fittings and paint
3 weeks · 12% of the contract
week 21 to 23
-
08 / 8
Snag list and handover
3 weeks · 10% of the contract
week 24 to 26
- Today
Stage payments on this job
5% is held back from every stage payment as retention and released
90 days after handover.
3 variations signed on this job so far, worth
JMD 615,000, added to the contract sum above.
Weather days used: 4 of 5.
About this job
A house on a slope, which meant a retaining wall to the rear before anything else could start. That wall was priced as its own line and signed before we broke ground.Four weather days went on the roof in June. The programme absorbed them, so the handover date has not moved.
Returning client, second house · Six on site, painters finishing · This job on its own page