Done this week. Second coat of paint through the bedrooms, kitchen doors adjusted, the external tap moved to the side the hose actually reaches, and the electrical certificate issued.
Snag list. Nineteen items received Monday. Eleven cleared. The three that need the tiler are booked for Tuesday and the two door frames go back to the joiner on Monday.
Next week. Clear the rest of the list, clean through, and fill the water tank so the pump can be tested under load.
Handover. Still the Friday of week twenty-six, as programmed in January. Retention of five per cent is held for ninety days after that.