Jacks Hill one-storey house

One-storey house, 148 m², twenty-six week programme, at handover.

Build type
One-storey block house
Area
148 m²
Contract sum
JMD 22,940,000
Programme
26 weeks
Variations signed
3
Weather days used
4 of 5

Jacks Hill one-storey house

One-storey block house · 148 m²
Contract JMD 22,940,000 · 26 week programme
Started 02 Apr 2026, Six on site, painters finishing

26 weeks Programme signed at contract
Handover is week 26
  1. 01 / 8 Set out, footings and foundation 3 weeks · 10% of the contract week 1 to 3
  2. 02 / 8 Blockwork to ring beam 4 weeks · 15% of the contract week 4 to 7
  3. 03 / 8 Roof or suspended slab 3 weeks · 15% of the contract week 8 to 10
  4. 04 / 8 Windows, doors and external render 3 weeks · 12% of the contract week 11 to 13
  5. 05 / 8 Plumbing and electrical rough-in 3 weeks · 12% of the contract week 14 to 16
  6. 06 / 8 Plaster, screed and tiling 4 weeks · 14% of the contract week 17 to 20
  7. 07 / 8 Joinery, fittings and paint 3 weeks · 12% of the contract week 21 to 23
  8. 08 / 8 Snag list and handover 3 weeks · 10% of the contract week 24 to 26

Stage payments on this job

StageSharePayment, JMDStatus
Set out, footings and foundationSigned off: Engineer, steel before the pour 10% 2,294,000 After week 3 sign-off
Blockwork to ring beamSigned off: Client walks the openings 15% 3,441,000 After week 7 sign-off
Roof or suspended slabSigned off: Watertight after rain 15% 3,441,000 After week 10 sign-off
Windows, doors and external renderSigned off: Openings sealed, render cured 12% 2,752,800 After week 13 sign-off
Plumbing and electrical rough-inSigned off: Pressure test, wall photographs 12% 2,752,800 After week 16 sign-off
Plaster, screed and tilingSigned off: Shower flood test, tile set-out 14% 3,211,600 After week 20 sign-off
Joinery, fittings and paintSigned off: Electrical certificate 12% 2,752,800 After week 23 sign-off
Snag list and handoverSigned off: Client snag list cleared 10% 2,294,000 After week 26 sign-off
Contract sum, fixed at signing 100% 22,940,000 Invoiced stage by stage

5% is held back from every stage payment as retention and released 90 days after handover. 3 variations signed on this job so far, worth JMD 615,000, added to the contract sum above. Weather days used: 4 of 5.

Jacks Hill one-storey house under construction

This job

A house on a slope, which meant a retaining wall to the rear before anything else could start. That wall was priced as its own line and signed before we broke ground.

Four weather days went on the roof in June. The programme absorbed them, so the handover date has not moved.

Returning client, second house · Six on site, painters finishing