Friday report, 07 Sep 2026. Jacks Hill one-storey house, week 23.

Done this week. Kitchen carcasses and worktop fitted, sanitary ware and taps installed and tested, switch plates on, and the first coat of paint through the whole house.

Next week. Your walk-through is Monday at nine. Bring a notebook and be hard on us. The list you write on Monday is the list we clear, and anything you miss is easier for everyone if it is on that sheet.

Weather. Nothing lost. Four weather days used on this job in total, out of five in the contract.