Done this week. Formwork struck to the first floor slab and the props left in under the long span until Monday. Steel fixed to the upper ring beam and inspected Thursday morning. Blockwork started to the rear bedrooms.
Next week. Pour the upper ring beam Tuesday, weather allowing, then block the front elevation. The window schedule goes to the supplier Monday so the frames are on site for week fifteen.
Materials on site. Steel for the roof, 40 bags of cement, blocks for the rear wall. Nothing outstanding from suppliers.
Weather. Two hours lost Wednesday afternoon. Not a weather day.
Money. Stage three is not complete, so nothing is due this week. The carport light variation is priced at 148,000 and is with you to sign.