Shortwood Road, week four

Friday report, 14 Sep 2026. Shortwood Road shop fit-out, week 4.

Done this week. Partition track set out and checked against the dispensary layout, first side of board up in the two consulting rooms, and the old floor screed broken out where the levels were 40 mm off.

Next week. Second side of board, ceiling grid, and the electrician starts containment above the grid. The landlord has been given the dates for the two evenings we need the water off.

Lead items. Shopfront glass confirmed for week thirteen. Dispensary joinery in production, delivery week fifteen.

Weather. No time lost. This job is inside.

Money. Stage two completes next Friday. The invoice will follow the sign-off, not precede it.