Shortwood Road shop fit-out

Light commercial fit-out, 96 m², eighteen week programme.

Build type
Shop or office fit-out
Area
96 m²
Contract sum
JMD 14,880,000
Programme
18 weeks
Variations signed
1
Weather days used
0 of 5

Shortwood Road shop fit-out

Shop or office fit-out · 96 m²
Contract JMD 14,880,000 · 18 week programme
Started 20 Aug 2026, Five on site

18 weeks Programme signed at contract
Handover is week 18
  1. 01 / 8 Set out, footings and foundation 2 weeks · 10% of the contract week 1 to 2
  2. 02 / 8 Blockwork to ring beam 3 weeks · 15% of the contract week 3 to 5
  3. 03 / 8 Roof or suspended slab 2 weeks · 15% of the contract week 6 to 7
  4. 04 / 8 Windows, doors and external render 2 weeks · 12% of the contract week 8 to 9
  5. 05 / 8 Plumbing and electrical rough-in 2 weeks · 12% of the contract week 10 to 11
  6. 06 / 8 Plaster, screed and tiling 3 weeks · 14% of the contract week 12 to 14
  7. 07 / 8 Joinery, fittings and paint 2 weeks · 12% of the contract week 15 to 16
  8. 08 / 8 Snag list and handover 2 weeks · 10% of the contract week 17 to 18

Stage payments on this job

StageSharePayment, JMDStatus
Set out, footings and foundationSigned off: Engineer, steel before the pour 10% 1,488,000 After week 2 sign-off
Blockwork to ring beamSigned off: Client walks the openings 15% 2,232,000 After week 5 sign-off
Roof or suspended slabSigned off: Watertight after rain 15% 2,232,000 After week 7 sign-off
Windows, doors and external renderSigned off: Openings sealed, render cured 12% 1,785,600 After week 9 sign-off
Plumbing and electrical rough-inSigned off: Pressure test, wall photographs 12% 1,785,600 After week 11 sign-off
Plaster, screed and tilingSigned off: Shower flood test, tile set-out 14% 2,083,200 After week 14 sign-off
Joinery, fittings and paintSigned off: Electrical certificate 12% 1,785,600 After week 16 sign-off
Snag list and handoverSigned off: Client snag list cleared 10% 1,488,000 After week 18 sign-off
Contract sum, fixed at signing 100% 14,880,000 Invoiced stage by stage

5% is held back from every stage payment as retention and released 90 days after handover. 1 variation signed on this job so far, worth JMD 92,500, added to the contract sum above. Weather days used: 0 of 5.

Shortwood Road shop fit-out under construction

This job

A pharmacy going into a shell unit. The landlord allows work from seven to five on weekdays only, so the programme is built on weekday hours and nothing is promised for a Saturday.

The shopfront glass is a twelve week lead item and was ordered in week one, before we broke a single wall.

Pharmacy, first branch · Five on site