180 m² of rental flats over a double garage. Nine days of rain in October went straight into the roof stage and we only had five weather days in the contract, so the job finished two weeks after the programme date. The client had that in writing in week thirty-one, not at handover.
The three variations were a second water tank, a change to the stair balustrade and an extra circuit for a future inverter.