Skip to content
Level Building contractor · Kingston Price my drawings

Beechwood Avenue, week ten

Friday report, 07 Sep 2026. Beechwood Avenue, Kingston 8, week 10.

Done this week. First floor slab poured Tuesday from seven in the morning, finished by two, and kept wet under sheeting for three days. Cube samples taken and sent for testing.

Next week. Strike the formwork, leave the props in under the long span, start the upper ring beam steel.

Weather. Nothing lost.

Money. Nothing due. Stage three completes when the roof is on and has taken rain.

Every report This job's programme